Key dates in Sydney's WestConnex project

AAP

Powered by

KEY DATES FOR SYDNEY'S WESTCONNEX MOTORWAY PROJECT:

* King Georges Road interchange construction began in July 2015 and was completed in early 2017

* M4 widening started in 2015 and is expected to open in next two months

Advertisement

* M4 East construction started in March 2016 and is due to open in 2019

* New M5 construction began in July 2016, with an expected completion date in early 2020

* M4-M5 link construction set to start in 2018, with completion by 2023

* No construction start date listed for Sydney Gateway, but the NSW government says it's committed to providing the project by 2023.